GTA developments 2026–2028: what’s actually approved and being built
Permits issued, projects under construction and Council approvals across the GTA, each checked on an official source. Proposals are labelled as proposals.

At a glance: most “coming soon” claims are proposals. This tracker only lists projects with an official source, and it says exactly how far each one has got. A building permit is the strongest signal. Council approval is a permission, not a start date.
Checked on 3 October 2026. Updated monthly.
How to read a project’s stage
| Stage | What it means | Signal that it gets built 2026–2028 |
|---|---|---|
| Proposed / application | A landowner has asked for permission. It can be refused, cut down or take years. | Low |
| Council or Tribunal approved (official plan / zoning) | The use and height are permitted. No guarantee anyone builds soon. | Medium |
| Provincial zoning order (MZO) | The Province has zoned it directly, often at transit stations. | Medium |
| Site plan approved | Detailed design is signed off. Financing and sales usually come next. | Medium–high |
| Building permit issued / under construction | Construction is legally allowed and usually underway. | High |
If you are buying near a project, the stage tells you how much weight to give it. If you are a business owner, a permit-issued tower nearby means new customers in two to four years; an application means maybe.
The tracker: strongest projects by stage
Sorted from strongest signal (permit issued, under construction) to approved but not started.
| Where | Project | Size | Stage (official) |
|---|---|---|---|
| Toronto | Galleria Mall, 1245 Dupont St | Mall redevelopment; 31-storey tower (427 units), more towers applied for | Building permit issued Dec 2025 |
| Toronto | 53 Sheppard Ave W | 18 storeys, 415 units | Building permit issued Aug 2026 |
| Toronto | 1200 Sheppard Ave E (Phases 1–2) | 715 units in 2 towers | Building permits issued Jan and Sep 2026 |
| Toronto | 4630 Kingston Rd | 566 rental units | Building permit issued May 2026 |
| Toronto | Bloor–Kipling Block 1 | 725 rental units | Permit issued Feb 2026; occupancy targeted Q2 2027 |
| Toronto | 50 Wilson Heights Blvd | 1,527 units | Under construction |
| Toronto | 2444 Eglinton Ave E | 919 units | Under construction |
| Toronto | 777 Victoria Park Ave | 705 units | Under construction |
| Toronto | 610 Bay / 130 Elizabeth | 827 units | Under construction |
| Toronto | Cloverdale Mall | About 5,536 units | Council approved Feb 2026 |
| Toronto | Fairview Mall Phase 1A | 585 rental units | Council approved Apr 2026 |
| Toronto | 40 Bushby Dr | About 1,500 units | Council approved Jun 2026 |
| Toronto | Agincourt Mall | 4,372 units | Council approved Dec 2021; no permit yet |
| Toronto | Golden Mile, 1891 Eglinton Ave E | About 2,709 units | Settlement accepted Dec 2023; tower permit under review |
| Pickering | Pickering City Centre (mall) | About 6,000 units | Block 1 under construction since Sep 2025 |
| Pickering | Universal City | Condo towers | Permits issued, under construction |
| Ajax | 212 Bayly St W and 282 Monarch Ave | 962 + 865 units (33 storeys each) | Building permits under review |
| Ajax | 60 Blowers Cres | About 622 units | Approved May 2026 |
| Burlington | Fairview St & Drury Ln | 2,494 units in 7 towers | Site plan approved |
| Oakville | Oakville GO community | 11 towers, about 537,700 m² | Provincial zoning orders Apr 2026 |
| Mississauga | Lakeview Village | Up to 16,000 units | First 8,050 units approved 2024; site plans underway |
| Markham | CF Markville Phase 1 | About 1,881 units | Plan amendment adopted 2025; zoning reported Dec 2025 |
| Markham / Richmond Hill | Bridge and High Tech subway communities | Very large mixed-use (zoning orders) | Provincial zoning orders 2022; subway under construction |
| Clarington | Darlington small modular reactors | $20.9B, 4 reactors (major employer) | Under construction |
Own a home or plaza near one of these projects? Get a written view of where it sits today.
Get my price rangeTransit that is open vs. under construction
- Open: Line 5 Eglinton (Feb 2026) and Line 6 Finch West (Dec 2025).
- Under construction, no official opening year: Ontario Line, Scarborough Subway Extension, Eglinton West extension, Yonge North Subway Extension, Hazel McCallion LRT and the GO extension to Bowmanville.
- Under construction with published windows: the Durham-Scarborough rapid bus in Ajax and Pickering (2025–2028).
- Highway 413: construction started (Ontario 2026 Budget).
Ads that promise a “subway opening in 2028” are not quoting an official date. Ask for the source.
How serious buyers use this
- Resale near a permitted project: expect 2–4 years of construction disruption, then new amenities and more competition from new units. Price both into the decision.
- Pre-construction: a project inside an approved transit community still needs a builder licence, a deposit plan and an occupancy date you can live with. Read the pre-construction guide.
- Commercial: new towers with podium retail need tenants. Grocery, daycare, clinic and food operators can negotiate early. See mall and plaza redevelopments.
- Land and plazas: older plazas near approved transit stations are where rezoning pressure is highest. Valuation depends on the lease roll and zoning, not just land size.
City-by-city detail
Every GTA municipality has its own guide with the full project list, transit, tax rate and business incentives: Toronto, Scarborough, North York, Etobicoke, Mississauga, Brampton, Markham, Vaughan, Richmond Hill, Oakville, Burlington, Pickering, Ajax and more on the Guides page.
Read next: GTA mall and plaza redevelopments: the 2026 list
General information, not investment or legal advice. Planning approvals and construction timelines change; confirm the current status with the municipality before relying on it. Inderpal Sidhu, Salesperson · HomeLife Silvercity Realty Inc., Brokerage.
Sources
City of Toronto: Active building permits (open data)
City of Toronto: Housing Now progress update, Jul 2026
Speak with Inderpal Sidhu
Direct: (647) 338-6875 · Office: (647) 931-5918
WhatsApp · Get my price range
Inderpal Sidhu, Salesperson · HomeLife Silvercity Realty Inc., Brokerage. Not intended to solicit properties or clients already under contract with another brokerage.
Related guides

GTA mall and plaza redevelopments: the 2026 list
Twenty sites, their real stage, and what it means for tenants and owners.
Read the guide
Ontario pre-construction buyer guide 2026
Builder check, deposit protection, cooling-off, delays, assignments and HST rebates.
Read the guide
GTA housing market update: September 2026
Sales, prices and inventory by region and property type, and what they mean.
Read the guide